How Top Down Estimation in Primavera P6 works

Top Down Estimation in Primavera P6

How Top Down Estimation in Primavera P6 works

Top Down Estimation in Primavera P6

In Primavera, there is a function called Top Down Estimation, which helps you calculate an estimated figure for Labor and Non-labor unit based on “estimation weights”. Top Down Estimation can be applied to both the WBS and Activity.

I will show you how Top Down Estimation works in Primavera P6.

Consider a simple project, where each activity is assigned the resource “Test”.

By default, each activity has 40 units.


We will use Top Down Estimation to redistribute the units to make it more realistic.

To perform top down estimation, you must first assign estimation weights to WBS and activities. These estimation weights are used to determine how units are distributed among WBS and activities.

Step 1:

Go to the WBS window and add the “Est Weight” as a column.


Step 2:

Now enter the weight for each WBS.


Step 3:

Next, go to the Activities window. Add “Est Weight” column.

P6 Top-Down Estimation- Image 04


Step 4:

Now enter the weight for each activity.

P6 Top-Down Estimation- Image 05


Step 5:

Go to Tool -> Top Down Estimation


Step 6:

Primavera displays the current units in your project. Now you can enter the new units you want to apply to your project.


Step 7:

Click on the Apply button.

Now you can see WBS and activities have new budgeted units.

P6 Top-Down Estimation- Image 08

The units are distributed according to Est Weight that you assigned.

For example: Foundation get 40% of 1000 units = 400 units. Bored Pile get 70% of 400 units = 280 units.

I hope now you have a better idea of how Top down estimation works in Primavera P6.

If you have any question, please post them down below. I will make sure that I will go through as many questions as I can and assist you in answering your questions.

Additional Resources:

If you are keen on mastering your skills in project scheduling with Primavera P6 and getting equipped with new and proven strategies in cutting the time in schedule development, updating, and reporting, check this comprehensive and hands-on training program offered by Project Control Academy; Practical Project Scheduling with Primavera P6 Online Training.
 
 
Practical Project Scheduling with Primavera P6 Online Training 


About the Author, Khuong Do

Khuong Do is a Project Planner in Civil Engineering, Transportation, and Oil & Gas Industry. He has worked as a Primavera Consultant Specialist since 2006 and willing to share his passion for Primavera through lots of Tips & Trick on his personal blog.

He holds a Civil Engineering degree and a Bachelor of Information Management System. Now he is working in Petronas RAPID project, one of the biggest Refinery and Petrochemical complex, in Pengerang – Malaysia

Recent Blog Posts

AI in Project Controls: Are You Preparing for the Future—or Falling Behind?

Are you frustrated that no one is bridging the gap between project controls and project management teams in your organization? Find out how you can be that person.

Read More »

Are you frustrated that no one is bridging the gap between project controls and project management teams in your organization? Find out how you can be that person.

Read More »

Are you frustrated that no one is bridging the gap between project controls and project management teams in your organization? Find out how you can be that person.

Read More »
The Best Project Controls Conferences

Are you considering attending a Project Controls conference in 2025? Whether you’re looking to sharpen your skills, discover the latest industry trends, or connect with like-minded professionals, conferences are one of the best ways to elevate your career. Every time I attend a conference, I’m reminded of how energizing and

Read More »

Does it baffle you that project resource shortages continue to cause time and cost overruns despite technological advances? Find out why in our blog post.

Read More »
Excelling in Your Project Professional Career: The Secret to True Leadership and Success

Does it baffle you that project resource shortages continue to cause time and cost overruns despite technological advances? Find out why in our blog post.

Read More »
Leading Without a Title: Unlocking the Power of Influence

Learn how to lead without a formal title by mastering influence, emotional intelligence, and communication. Discover practical tips to make an impact in your project team and career.

Read More »

Check this blog post to explore a simple principle that will guide cost estimating best practices, ultimately empowering decision-makers with the insights needed to make informed judgments.

Read More »
LinkedIn
Facebook
Twitter
WhatsApp
Email
>