How to update the Baseline Schedule in Primavera P6?

How to update the Baseline Schedule in Primavera P6

How to update the Baseline Schedule in Primavera P6?

How to update the Baseline Schedule in Primavera P6

The baseline Schedule is something we usually do not change. However, in some cases, schedule rebaselining might be required.

In this post, I will show you how to update the baseline schedule in Primavera P6.

Consider a simple project, which has a baseline assigned as illustrated below:


After several update periods, the project is delayed quite far from the baseline.


After discussion with the Owner, they authorized us to rebaseline the schedule and update our baseline to be identical to the current schedule.

There are some ways to update the baseline in Primavera P6.

Option 1: Creating a new baseline based on the current schedule and assign the new baseline to the project.

In this case, first, you have to make an important configuration.

Go to the menu Admin -> Admin Preferences.

In Earned Value tab, select “At completion values with current dates”


Go to menu Project -> Maintain Baselines.

Click on “Add” to create a new baseline


Go to the menu Project -> Assign Baselines. Select baseline B2


Now you can see the baseline have been updated


Option 2: Restore the baseline

Go to the menu Project -> Assign Baselines. Select Current project


Go to menu Project -> Maintain Baselines.

Select the baseline and click on the “Restore” button.


Now go to the Project window. You will see the baseline become a normal project which you can open and update easily.


After updating and finalizing the new baseline schedule, you need to convert it to a baseline again. To do so, Open your “main” project. Go to the menu Project -> Maintain Baselines. Click on the “Add” button.

Now select the option “Convert another project…”


And select the updated baseline project.


Now your project will have a new baseline.

This is how you can update your baseline schedule.

If you have any question, please post them down below. I will make sure that I will go through as many questions as I can and assist you in answering your questions.

Additional Resources:

If you are keen on mastering your skills in project scheduling with Primavera P6 and getting equipped with new and proven strategies in cutting the time in schedule development, updating, and reporting, check this comprehensive and hands-on training program offered by Project Control Academy; Practical Project Scheduling with Primavera P6 Online Training.
 
 

 

About the Author, Khuong Do

Khuong Do is a Project Planner in Civil Engineering, Transportation, and Oil & Gas Industry. He has worked as a Primavera Consultant Specialist since 2006 and willing to share his passion for Primavera through lots of Tips & Trick on his personal blog.

He holds a Civil Engineering degree and a Bachelor of Information Management System. Now he is working in Petronas RAPID project, one of the biggest Refinery and Petrochemical complex, in Pengerang – Malaysia.

Recent Blog Posts

Discover how Project Control Summit inspired the Major Projects Podcast and sparked conversations about real-world project management experiences.

Read More »

AI is moving fast, but many project controls teams are still stuck with scattered files, manual reports, reactive reviews, and delayed insights. This article shows six practical AI shifts that can help you save time, improve analysis, and build the skills needed to stay ahead.

Read More »
Project scheduler reviewing a Gantt chart for forensic schedule analysis, delay analysis, and critical path impact in a project delay claim.

Learn the difference between delay analysis and forensic schedule analysis, and why schedulers, planners, and project controls professionals must prove causation, critical path impact, and delay entitlement.

Read More »
AI in Project Controls: Are You Preparing for the Future—or Falling Behind?

AI in Project Controls is transforming how we manage projects. Learn what it is, why it matters, and how to prepare to stay ahead.

Read More »

Think EVM is only for government projects or too complex? Discover the truth behind the most common Earned Value Management Myths.

Read More »

Learn how to integrate project controls into contract management—from scope and risk alignment to change control—for better project delivery.

Read More »
The Best Project Controls Conferences

Are you considering attending a Project Controls conference in 2025? Whether you’re looking to sharpen your skills, discover the latest industry trends, or connect with like-minded professionals, conferences are one of the best ways to elevate your career. Every time I attend a conference, I’m reminded of how energizing and

Read More »

InEight and Project Control Academy have joined forces in a strategic partnership aimed at advancing and standardizing technology implementation best practices in the field of project controls.

Read More »
LinkedIn
Facebook
Twitter
WhatsApp
Email

Our Biggest Thanksgiving Sale Is ON! Save Up to 60% on Project Controls Training Programs & Packages.

Close Welcome Bar